Infrastructure Projects (Completed)
Location : Paseo Ortiz St., Maduya, Brgy. 9, Carmona, Cavite
Contractor : T.E Trinidad Construction
IMPLEMENTATION SCHEDULE
NTP Date : 3/2/2022
No. of CD : 90 CD
Date Started : 2/21/2022
Target Completion Date : 5/22/2022
PROJECT STATUS
Source of Fund : MDRRM
% of Completion : 100%
Project Cost : 3,691,518.30
Remarks : Completed
Location : Brgy. Cabilang Baybay
Contractor : DCR Construction
IMPLEMENTATION SCHEDULE
NTP Date : 11/23/2021
No. of CD : 118 CD
Date Started : 11/23/2021
Target Completion Date : 03/21/2022
PROJECT STATUS
Source of Fund : LGSF-AM
% of Completion : 100%
Project Cost : 4,952,053.51
Remarks : Completed
Location : Covered Court, Brgy. 8
Contractor : RMDL Bldg. & Const. Co.
IMPLEMENTATION SCHEDULE
NTP Date : 4/2/2022
No. of CD : 66 CD
Date Started : 4/2/2022
Target Completion Date : 6/7/2022
PROJECT STATUS
Source of Fund : MDF
% of Completion : 100%
Project Cost : 2,238,312.56
Remarks : Completed
Location : Paligawan, Lantic, Brgy. 13
Contractor : T.E Trinidad Construction
IMPLEMENTATION SCHEDULE
NTP Date : 3/11/2022
No. of CD : 30 CD
Date Started : 3/11/2022
Target Completion Date : 4/10/2022
PROJECT STATUS
Source of Fund : LSB
% of Completion : 100%
Project Cost : 832,466.25
Remarks : Completed
Location : Mayor’s Blvd., Maduya, Brgy. 9, Carmona, Cavite
Contractor : T.E Trinidad Construction
IMPLEMENTATION SCHEDULE
NTP Date : 3/2/2022
No. of CD : 35 CD
Date Started : 3/2/2022
Target Completion Date : 4/6/2022
PROJECT STATUS
Source of Fund : MDRRM
% of Completion : 100%
Project Cost : 1,191,490.86
Remarks : Completed
Location : J.M. Loyola St., Brgy. 4, Carmona, Cavite
Contractor : Protech Const.
IMPLEMENTATION SCHEDULE
NTP Date : 3/23/2022
No. of CD : 60 CD
Date Started : 3/23/2022
Target Completion Date : 5/22/2022
PROJECT STATUS
Source of Fund : LSB
% of Completion : 100%
Project Cost : 3,110,395.80
Remarks : Completed
Location : Maduya, Brgy. 9, Carmona, Cavite
Contractor : T.E Trinidad Construction
IMPLEMENTATION SCHEDULE
NTP Date : 3/17/2022
No. of CD : 20 CD
Date Started : 3/17/2022
Target Completion Date : 4/6/2022
PROJECT STATUS
Source of Fund : LSB
% of Completion : 100%
Project Cost : 547,310.66
Remarks : Completed
Location : Bancal, Brgy. 14, Carmona, Cavite
Contractor : T.E Trinidad Construction
IMPLEMENTATION SCHEDULE
NTP Date : 3/23/2022
No. of CD : 40 CD
Date Started : 3/23/2022
Target Completion Date : 5/2/2022
PROJECT STATUS
Source of Fund : LSB
% of Completion : 100%
Project Cost : 1,003,784.25
Remarks : Completed
Location : Mabuhay, Brgy. 11, Carmona, Cavite
Contractor : T.E Construction
IMPLEMENTATION SCHEDULE
NTP Date : 3/24/2022
No. of CD : 50 CD
Date Started : 3/24/2022
Target Completion Date : 5/13/2022
PROJECT STATUS
Source of Fund : LSB
% of Completion : 100%
Project Cost : 1,294,892.81
Remarks : Completed
Location : Milagrosa, Brgy. 12, Carmona, Cavite
Contractor : T.E Trinidad Construction
IMPLEMENTATION SCHEDULE
NTP Date : 3/24/2022
No. of CD : 45 CD
Date Started : 3/24/2033
Target Completion Date : 5/8/2022
PROJECT STATUS
Source of Fund : LSB
% of Completion : 100%
Project Cost : 993,678.00
Remarks : Completed
Location : Cabilang Baybay, Brgy. 10, Carmona, Cavite
Contractor : T.E Trinidad Construction
IMPLEMENTATION SCHEDULE
NTP Date : 3/23/2022
No. of CD : 55 CD
Date Started : 3/23/2022
Target Completion Date : 5/17/2022
PROJECT STATUS
Source of Fund : LSB
% of Completion : 100%
Project Cost : 1,396,448.81
Remarks : Completed
Location : Lantic, Brgy. 13, Carmona, Cavite
Contractor : T.E Trinidad
IMPLEMENTATION SCHEDULE
NTP Date : 3/23/2022
No. of CD : 40 CD
Date Started : 3/23/2022
Target Completion Date : 5/2/2022
PROJECT STATUS
Source of Fund : LSB 100%
% of Completion : 100%
Project Cost : 1,092,866.91
Remarks : Completed
Location : Brgy. 8, Carmona, Cavite
Contractor : T.E Trinidad Construction
IMPLEMENTATION SCHEDULE
NTP Date : 3/24/2022
No. of CD : 35 CD
Date Started : 3/24/2022
Target Completion Date : 4/28/2022
PROJECT STATUS
Source of Fund : LSB
% of Completion : 100%
Project Cost : 1,195,641.56
Remarks : Completed
Location : Paligawan Matanda, Brgy. 13, Carmona, Cavite
Contractor : T.E Trinidad Construction
IMPLEMENTATION SCHEDULE
NTP Date : 50 CD
No. of CD : 3/24/2022
Date Started : 3/24/2022
Target Completion Date : 5/13/2022
PROJECT STATUS
Source of Fund : LSB
% of Completion : 100%
Project Cost : 1,195,641.56
Remarks : Completed
Location : Brgy. 8, Carmona, Cavite
Contractor : T.E Trinidad
IMPLEMENTATION SCHEDULE
NTP Date : 3/24/2022
No. of CD : 60 CD
Date Started : 3/24/2022
Target Completion Date : 5/23/2022
PROJECT STATUS
Source of Fund : LSB
% of Completion : 100%
Project Cost : 1,292,437.47
Remarks : Completed
Location : Patindig Araw, Milagrosa, Brgy. 12, Carmona, Cavite
Contractor : Omnicon Builders
IMPLEMENTATION SCHEDULE
NTP Date : 6/13/2022
No. of CD : 45 CD
Date Started : 6/13/2022
Target Completion Date : 7/28/2022
PROJECT STATUS
Source of Fund : LGU
% of Completion : 100%
Project Cost : 747,227.71
Remarks : Completed
Location : Mayors Blvd., Maduya, Brgy. 9, Carmona, Cavite
Contractor : T.E Trinidad
IMPLEMENTATION SCHEDULE
NTP Date : 6/20/2022
No. of CD : 60 CD
Date Started : 6/20/2022
Target Completion Date : 8/19/2022
PROJECT STATUS
Source of Fund : LGU
% of Completion : 100%
Project Cost : 4,433,948.53
Remarks : Completed
Location : Municipal Compound, Brgy. 4, Carmona, Cavite
Contractor : T.E Trinidad Construction
IMPLEMENTATION SCHEDULE
NTP Date : 6/21/2022
No. of CD : 25 CD
Date Started : 6/21/2022
Target Completion Date : 7/16/2022
PROJECT STATUS
Source of Fund : LGU
% of Completion : 100%
Project Cost : 1,059,279.20
Remarks : Completed
Location : Mayor’s Blvd., Maduya, Brgy. 9, Carmona, Cavite
Contractor : T.E Trinidad
IMPLEMENTATION SCHEDULE
NTP Date : 6/28/2022
No. of CD : 20 CD
Date Started : 6/28/2022
Target Completion Date : 7/18/2022
PROJECT STATUS
Source of Fund : LGU
% of Completion : 100%
Project Cost : 580,202.47
Remarks : Completed
Location : Angelo L. Loyoa Senior High School, Lantic, Brgy. 13, Carmona, Cavite
Contractor : Omnicon Builders
IMPLEMENTATION SCHEDULE
NTP Date : 6/28/2022
No. of CD : 45 CD
Date Started : 6/28/2022
Target Completion Date : 8/12/2022
PROJECT STATUS
Source of Fund : LGU
% of Completion : 100%
Project Cost : 1,517,607.39
Remarks : Completed
Location : Motorpool Bldg., Mayor’s Blvd., Maduya, Brgy. 9, Carmona, Cavite
Contractor : Omnicon Builders
IMPLEMENTATION SCHEDULE
NTP Date : 8/8/2022
No. of CD : 40CD
Date Started : 6/29/2022
Target Completion Date : 9/17/2022
PROJECT STATUS
Source of Fund : LGU
% of Completion : 100%
Project Cost : 1,970,900.24
Remarks : Completed
Location : Carmona Town Plaza, Brgy., 4, Carmona, Cavite
Contractor : Fe S. Reyes General Contractor
IMPLEMENTATION SCHEDULE
NTP Date : 8/10/2022
No. of CD : 30CD
Date Started : 6/30/2022
Target Completion Date : 9/9/2022
PROJECT STATUS
Source of Fund : LGU
% of Completion : 100%
Project Cost : 1,756,377.00
Remarks : Completed
INFRASTRUCTURE PROJECTS (On-Going)
Location : Altarez, Maduya, Brgy. 9, Carmona, Cavite
Contractor : DCR Construction
IMPLEMENTATION SCHEDULE
NTP Date : 2/21/2022
No. of CD : 160 CD
Date Started : 2/21/2022
Target Completion Date : 7/31/2022
PROJECT STATUS
Source of Fund : MDF
% of Completion : 90%
Project Cost : 4,244,238.35
Remarks : On-Going
Location : Townhomes, Milagrosa, Brgy. 12, Carmona, Cavite
Contractor : DCR Construction
IMPLEMENTATION SCHEDULE
NTP Date : 3/1/2022
No. of CD : 120CD
Date Started : 3/1/2022
Target Completion Date : 6/29/2022
PROJECT STATUS
Source of Fund : MDF
% of Completion : 78.08%
Project Cost : 3,272,607.62
Remarks : On-Going
Location : Townhomes, Milagrosa, Brgy. 12, Carmona, Cavite
Contractor : DCR Construction
IMPLEMENTATION SCHEDULE
NTP Date : 7/11/2022
No. of CD : 120 CD
Date Started : 7/11/2022
Target Completion Date : 11/8/2022
PROJECT STATUS
Source of Fund : LGU
% of Completion : 39.80%
Project Cost : 2,825,077.09
Remarks : On-Going
Location : Phase 2, Milagrosa, Brgy. 12, Carmona, Cavite
Contractor : Protech Const. and Devt. Corp.
IMPLEMENTATION SCHEDULE
NTP Date : 7/20/2022
No. of CD : 105CD
Date Started : 7/20/2022
Target Completion Date : 11/2/2022
PROJECT STATUS
Source of Fund : LGU
% of Completion : 54.94%
Project Cost : 2,989,472.43
Remarks : On-Going