Infrastructure Projects (Completed)

Location : Paseo Ortiz St., Maduya, Brgy. 9, Carmona, Cavite

Contractor : T.E Trinidad Construction

IMPLEMENTATION SCHEDULE

NTP Date : 3/2/2022

No. of CD : 90 CD

Date Started : 2/21/2022

Target Completion Date : 5/22/2022

PROJECT STATUS

Source of Fund : MDRRM

% of Completion : 100%

Project Cost : 3,691,518.30

Remarks : Completed

Location : Brgy. Cabilang Baybay

Contractor : DCR Construction

IMPLEMENTATION SCHEDULE

NTP Date : 11/23/2021

No. of CD : 118 CD

Date Started : 11/23/2021

Target Completion Date : 03/21/2022

PROJECT STATUS

Source of Fund : LGSF-AM

% of Completion : 100%

Project Cost : 4,952,053.51

Remarks : Completed

Location : Covered Court, Brgy. 8 

Contractor : RMDL Bldg. & Const. Co.

IMPLEMENTATION SCHEDULE

NTP Date : 4/2/2022

No. of CD : 66 CD

Date Started : 4/2/2022

Target Completion Date : 6/7/2022

PROJECT STATUS

Source of Fund : MDF

% of Completion : 100%

Project Cost : 2,238,312.56

Remarks : Completed

Location : Paligawan, Lantic, Brgy. 13

Contractor : T.E Trinidad Construction

IMPLEMENTATION SCHEDULE

NTP Date : 3/11/2022

No. of CD : 30 CD

Date Started : 3/11/2022

Target Completion Date : 4/10/2022

PROJECT STATUS

Source of Fund : LSB

% of Completion : 100%

Project Cost : 832,466.25

Remarks : Completed

Location :  Mayor’s Blvd., Maduya, Brgy. 9, Carmona, Cavite

Contractor : T.E Trinidad Construction

IMPLEMENTATION SCHEDULE

NTP Date : 3/2/2022

No. of CD : 35 CD

Date Started : 3/2/2022

Target Completion Date : 4/6/2022

PROJECT STATUS

Source of Fund : MDRRM

% of Completion : 100%

Project Cost : 1,191,490.86

Remarks : Completed

Location : J.M. Loyola St., Brgy. 4, Carmona, Cavite

 

Contractor : Protech Const.

 

IMPLEMENTATION SCHEDULE

 

NTP Date : 3/23/2022

 

No. of CD : 60 CD

 

Date Started : 3/23/2022

 

Target Completion Date : 5/22/2022

 

PROJECT STATUS

 

Source of Fund : LSB

 

% of Completion : 100%

Project Cost : 3,110,395.80

Remarks : Completed

Location : Maduya, Brgy. 9, Carmona, Cavite

Contractor : T.E Trinidad Construction

IMPLEMENTATION SCHEDULE

NTP Date : 3/17/2022

No. of CD : 20 CD

Date Started : 3/17/2022

Target Completion Date : 4/6/2022

PROJECT STATUS

Source of Fund : LSB

% of Completion : 100%

Project Cost : 547,310.66

Remarks : Completed

Location : Bancal, Brgy. 14, Carmona, Cavite 

Contractor : T.E Trinidad Construction

IMPLEMENTATION SCHEDULE

NTP Date : 3/23/2022

No. of CD : 40 CD

Date Started : 3/23/2022

Target Completion Date : 5/2/2022

PROJECT STATUS

Source of Fund : LSB

% of Completion : 100%

Project Cost : 1,003,784.25

Remarks : Completed

Location : Mabuhay, Brgy. 11, Carmona, Cavite

Contractor : T.E Construction

IMPLEMENTATION SCHEDULE

NTP Date : 3/24/2022

No. of CD : 50 CD

Date Started : 3/24/2022

Target Completion Date : 5/13/2022

PROJECT STATUS

Source of Fund : LSB

% of Completion : 100%

Project Cost : 1,294,892.81

Remarks : Completed

Location : Milagrosa, Brgy. 12, Carmona, Cavite

Contractor : T.E Trinidad Construction

IMPLEMENTATION SCHEDULE

NTP Date : 3/24/2022

No. of CD : 45 CD

Date Started : 3/24/2033

Target Completion Date : 5/8/2022

PROJECT STATUS

Source of Fund : LSB

% of Completion : 100%

Project Cost : 993,678.00

Remarks : Completed

Location : Cabilang Baybay, Brgy. 10, Carmona, Cavite 

Contractor : T.E Trinidad Construction

IMPLEMENTATION SCHEDULE

NTP Date : 3/23/2022

No. of CD : 55 CD

Date Started : 3/23/2022

Target Completion Date : 5/17/2022

PROJECT STATUS

Source of Fund : LSB

% of Completion : 100%

Project Cost : 1,396,448.81

Remarks : Completed

Location : Lantic, Brgy. 13, Carmona, Cavite

Contractor : T.E Trinidad

IMPLEMENTATION SCHEDULE

NTP Date : 3/23/2022

No. of CD : 40 CD

Date Started : 3/23/2022

Target Completion Date : 5/2/2022

PROJECT STATUS

Source of Fund : LSB 100%

% of Completion : 100%

Project Cost : 1,092,866.91

Remarks : Completed

Location : Brgy. 8, Carmona, Cavite

Contractor : T.E Trinidad Construction

IMPLEMENTATION SCHEDULE

NTP Date : 3/24/2022

No. of CD : 35 CD

Date Started : 3/24/2022

Target Completion Date : 4/28/2022

PROJECT STATUS

Source of Fund : LSB

% of Completion : 100%

Project Cost : 1,195,641.56

Remarks : Completed

Location : Paligawan Matanda, Brgy. 13, Carmona, Cavite

Contractor : T.E Trinidad Construction

IMPLEMENTATION SCHEDULE

NTP Date : 50 CD

No. of CD : 3/24/2022

Date Started : 3/24/2022

Target Completion Date : 5/13/2022

PROJECT STATUS

Source of Fund : LSB

% of Completion : 100%

Project Cost : 1,195,641.56

Remarks : Completed

Location : Brgy. 8, Carmona, Cavite

Contractor : T.E Trinidad

IMPLEMENTATION SCHEDULE

NTP Date : 3/24/2022

No. of CD : 60 CD

Date Started : 3/24/2022

Target Completion Date : 5/23/2022

PROJECT STATUS

Source of Fund : LSB

% of Completion : 100%

Project Cost : 1,292,437.47

Remarks : Completed

Location : Patindig Araw, Milagrosa, Brgy. 12, Carmona, Cavite

Contractor : Omnicon  Builders

IMPLEMENTATION SCHEDULE

NTP Date : 6/13/2022

No. of CD : 45 CD

Date Started : 6/13/2022

Target Completion Date : 7/28/2022

PROJECT STATUS

Source of Fund : LGU

% of Completion : 100%

Project Cost : 747,227.71

Remarks : Completed

Location : Mayors Blvd., Maduya, Brgy. 9, Carmona, Cavite

Contractor : T.E Trinidad

IMPLEMENTATION SCHEDULE

NTP Date : 6/20/2022

No. of CD : 60 CD

Date Started : 6/20/2022

Target Completion Date : 8/19/2022

PROJECT STATUS 

Source of Fund : LGU

% of Completion : 100%

Project Cost : 4,433,948.53

Remarks : Completed

Location : Municipal Compound, Brgy. 4, Carmona, Cavite

Contractor : T.E Trinidad Construction

IMPLEMENTATION SCHEDULE

NTP Date : 6/21/2022

No. of CD : 25 CD

Date Started : 6/21/2022

Target Completion Date : 7/16/2022

PROJECT STATUS

Source of Fund : LGU

% of Completion : 100%

Project Cost : 1,059,279.20

Remarks : Completed

Location : Mayor’s Blvd., Maduya, Brgy. 9, Carmona, Cavite

Contractor : T.E Trinidad

IMPLEMENTATION SCHEDULE

NTP Date : 6/28/2022

No. of CD : 20 CD

Date Started : 6/28/2022

Target Completion Date : 7/18/2022

PROJECT STATUS

Source of Fund : LGU

% of Completion : 100%

Project Cost : 580,202.47

Remarks : Completed

Location :  Angelo L. Loyoa Senior High School, Lantic, Brgy. 13, Carmona, Cavite

Contractor : Omnicon Builders

IMPLEMENTATION SCHEDULE

NTP Date : 6/28/2022

No. of CD : 45 CD

Date Started : 6/28/2022

Target Completion Date : 8/12/2022

PROJECT STATUS

Source of Fund : LGU

% of Completion : 100%

Project Cost : 1,517,607.39

Remarks : Completed

Location : Motorpool Bldg., Mayor’s Blvd., Maduya, Brgy. 9, Carmona, Cavite

Contractor : Omnicon Builders

IMPLEMENTATION SCHEDULE

NTP Date : 8/8/2022

No. of CD : 40CD

Date Started : 6/29/2022

Target Completion Date : 9/17/2022

PROJECT STATUS

Source of Fund : LGU

% of Completion : 100%

Project Cost : 1,970,900.24

Remarks : Completed

Location : Carmona Town Plaza, Brgy., 4, Carmona, Cavite

Contractor : Fe S. Reyes General Contractor

IMPLEMENTATION SCHEDULE

NTP Date : 8/10/2022

No. of CD : 30CD

Date Started : 6/30/2022

Target Completion Date : 9/9/2022

PROJECT STATUS

Source of Fund : LGU

% of Completion : 100%

Project Cost : 1,756,377.00

Remarks : Completed

INFRASTRUCTURE PROJECTS (On-Going)

Location : Altarez, Maduya, Brgy. 9, Carmona, Cavite

Contractor : DCR Construction

IMPLEMENTATION SCHEDULE

NTP Date : 2/21/2022

No. of CD : 160 CD

Date Started : 2/21/2022

Target Completion Date : 7/31/2022

PROJECT STATUS

Source of Fund : MDF

% of Completion : 90%

Project Cost : 4,244,238.35

Remarks : On-Going

Location : Townhomes, Milagrosa, Brgy. 12, Carmona, Cavite

Contractor : DCR Construction

IMPLEMENTATION SCHEDULE

NTP Date : 3/1/2022

No. of CD : 120CD

Date Started : 3/1/2022

Target Completion Date : 6/29/2022

PROJECT STATUS

Source of Fund : MDF

% of Completion : 78.08%

Project Cost : 3,272,607.62

Remarks : On-Going

Location : Townhomes, Milagrosa, Brgy. 12, Carmona, Cavite

Contractor : DCR Construction

IMPLEMENTATION SCHEDULE

NTP Date : 7/11/2022

No. of CD : 120 CD

Date Started : 7/11/2022

Target Completion Date : 11/8/2022

PROJECT STATUS

Source of Fund : LGU

% of Completion : 39.80%

Project Cost : 2,825,077.09

Remarks : On-Going

Location : Phase 2, Milagrosa, Brgy. 12, Carmona, Cavite

Contractor : Protech Const. and Devt. Corp.

IMPLEMENTATION SCHEDULE

NTP Date : 7/20/2022

No. of CD : 105CD

Date Started7/20/2022

Target Completion Date : 11/2/2022

PROJECT STATUS

Source of Fund : LGU

% of Completion : 54.94%

Project Cost : 2,989,472.43

Remarks : On-Going